# Rencana Tim — LMS MBG (Tim 4 + Agent) ## Peran & Tanggung Jawab - FE1: Learner flow, Course/Module, Desktop UX polishing. - FE2: Assessment (quiz/exam), Sertifikat, Analytics/Reward. - QA: Test case, UAT, regresi, pelaporan bug. - PM/Content: Scope, prioritas, konten, acceptance, koordinasi stakeholder. - Agent: Otomasi dokumen, scaffolding, patch kecil, monitoring lint/typecheck. ## Kapasitas & Komitmen - Sprint velocity target: ±16–20 story points/sprint (tim 4). - Jam fokus mingguan: 25–30 jam per anggota. ## Seremoni - Planning 2 jam (tiap awal sprint). - Daily 15 menit. - Review & Retro 1,5 jam (akhir sprint). ## RACI per Epik - A (Course): R-FE1, A-PM, C-QA, I-FE2. - B (Assessment): R-FE2, A-PM, C-QA, I-FE1. - C (Reward): R-FE2, A-PM, C-QA, I-FE1. - D (Analytics): R-FE2, A-PM, C-QA, I-FE1. - E (Desktop UX): R-FE1, A-PM, C-QA, I-FE2. - F (AI): R-FE2, A-PM, C-QA, I-FE1. - G (Schedule): R-FE1, A-PM, C-QA, I-FE2.